104
ACE – Kathy reached out to a new Habitat volunteer who works for ACE and things should be moving along better now.
Deck plans – arrived via email yesterday, but need signed and sealed copies now. Awaiting delivery.
Punch list status: Fans and lighting being ordered. Tom is ready to do instal and add crawl space and attic lighting. SJ Gas needs to be called to unlock and turn on. Shed permit submitted  03/15/2023. Checking with Lowe’s for shed materials. Build crawl space door and shed as soon as permit is approved. Order Levolor shades. Flooring can be ready in a few days, just call when needed. ReStore truck can pick-up and deliver. Check about underlayment and transitions for laundry and two baths. Driveway – crushed concrete already there under the sand. Check if driveway apron is required. Mailbox – add to Lowe’s list and quickset. Lawn seeding – Homeowner and crew. Possibly next weekend 03/25. Once flooring is in, schedule appliance move from ReStore to home. Manufacturer warranty for roof received from Dave Adams Roofing.
103
Plan status with twp – resolving questions from twp official to architect. Permit fee paid on 03/15/2023. Superior Walls deposit paid 03/09/23. Sub proposal status – latest deadline is 03/17
Electric – maybe two, one not interested, seeking third. Trusses – one received, one not interested. HVAC – One bid: equipment change and no air exchange system, awaiting a second contractor bid and another needs to breakdown the quote. Plumbing, sheetrock, and insulation still needed. Roof – contact Dave Adams Roofing. Tech school will either build walls on-site or off-site and transport as well. Septic & Well – request to township for copy of previously issued permit.
300 WW
Deposit received by JHand – needs property corners marked, will start demo and clearing around 03/20. House plan? Slimmer than Redwood dimensions, need to review HFHI library.
Sumner
Engineer discussion about green space and sewer with respect to CAFRA and ask about density. As of 03/10 no word. BP spoke with Dawn at MT MUA regarding capacity. Awaiting.
Construction Process
Architect availability – have on retainer, available to assist when needed. Schedule – more and longer work days. Volunteers – acclimating new vols, mentor rotation. Homeowner Construction Support Partner
Ramps
Temporary install completed and additional requests are trickling in, but out of income limits. Will pursue Univest to gauge interest in purchasing additional temporary ramp. Current homeowner will need a permanent ramp. Will pursue once 103 is underway and in motion.