As promised, we want to keep you all in the loop about where we stand with various projects so here goes:
104 E. Ocean – Modular
• Plumbing – initial work started, he will work with SJ Gas to run piping, will run stub for the HVAC and run water for outside spigot
• Electric – starts week of Jan 16th working with AC Electric to get meter ready to install
• HVAC – permit done, equipment to arrive within 10-14 days. Must have heat before hanging drywall
• SJ Gas has installed the gas meter although it may need to be relocated a bit higher due to grading around foundation
• AC Electric – Received contract and paid $8700 for them to run electric under the street awaiting date
• Decks -waiting for architectural plans for front and rear decks. Upon arrival Bill Patton will take to township and amend existing permit. Will begin construction as soon as received
• Estimated delivery date 8 weeks
103 E. Ocean – stick build
• Start in March
• Architectural plans in final stage – preliminary plans approved by township
• Superior Walls will be ordered as soon as permit is obtained
• Send out bids for sub-contractors
• Septic and well permits ordered
• Considering using roof trusses to give stand up attic as there will only be crawl space
• Electrician on-board and will work with students from CM Tech during installation
Wildwood Ave – stick build
• Permit to clear lot and remove existing structure obtained
• Tree Affect contacted for bid
• Will use existing plans and modify as needed.
• No room for deck – will install patio
Sumner Ave – 5 lots
• Filed the deed with Middle for properties
• DEP will give final approval when deed is approved
• Once approval is received, we will meet with Township Engineer with prospective plans to build 4-5 duplexes. If that fails, we will proceed with singles
As you can see, we are getting ahead of construction so that we can build one house right after another with little to no gap. We are financially able to this and are committed to do so. We are in the discussion phase with West Cape May to help the achieve their COAH requirements by end of 2025. We’ll keep you posted as discussions proceed.
– Dave Hammond, President