• March 9, 2023

Construction Update

Construction Update

Construction Update 150 150 Habitat for Humanity

104
ACE – conduit is installed, but no wiring. Deck plans – still haven’t received. Do we consider temporary alternative (pre-cast steps)? Interior punch list status: Homeowner has skilled family/friends to accomplish work for sweat equity, will review at Tuesday Construction Committee Meeting. Order Levolor shades from HFHI. Donated flooring from Artisan Floors and Interiors can be ready in a few days, will call when instal date is set after heat is available once electric is connected.. ReStore truck can pick-up and deliver. Driveway? Mailbox needs to be installed. Shed work can begin soon. Appliances can be brought over after floor is installed. Manufacturer warranty for roof requested from Dave Adams Co.
103
John checking on plan/permit status with Upper Twp. Superior Walls deposit paid 03/09/23. Sub proposal status will be discussed and reviewed on Tuesday at Construction Committee Meeting.
300 WW
Deposit received by JHand – needs property corners marked, will start demo and clearing approximately around 03/20. House plans selection underway. Can’t use Redwood dimensions are too wide.
Sumner
Number and type of housing to pursue still in investigative stage with engineer and township.